## 3.9 Current Status
|
|
|
<!---<mark>@ALP - not sure this makes us look good... completed subassemblies can be noted in relevant sections... maybe delete this section?</mark>
|
|
|
-->
|
|
|
|
|
|
- Cryostat
|
|
|
- Cart for the cryostat is fully assembled and in lab.
|
|
|
- Compressors and cold heads have been purchased and are stored in lab. Facilities upgrade to install the compressor and route cooling lines to the lab is in progress.
|
|
|
- Engineering drawings for mechanical design of the cryostat are being prepared to be sent to the machine shop.
|
|
|
|
|
|
<br>
|
|
|
|
|
|
- Dipole assemblies and 20K Interface
|
|
|
- All parts have been ordered and are expected to be delivered in early Oct.
|
|
|
|
|
|
<br>
|
|
|
|
|
|
- Cryo LNAs
|
|
|
- Completed full cryogenic testing of (10) prototypes
|
|
|
- Production run in progress, enclosures machined, electronics boards being assembled
|
|
|
|
|
|
<br>
|
|
|
|
|
|
- Internal Wiring
|
|
|
- Striplines and the custom connectors to be ordered imminently.
|
|
|
- Quotations for RF cables that would connect to the dipole/LNA output to striplines have been requested.
|
|
|
|
|
|
<br>
|
|
|
|
|
|
- Helium lines and associated fixtures for lab use are short lead time items, and would be ordered next quarter.
|
|
|
|
|
|
<br>
|
|
|
|
|
|
- GBT Interface
|
|
|
- We have completed preliminary design of the prime focus interface and verified that the ALPACA cryostat is compliant with requirements for installation at GBT prime focus.
|
|
|
- Detailed design and final checks will be conducted after this review as we have limited access to GBO personnel currently.
|
|
|
|
|
|